Crossrail to open ‘by March 2021’ without Bond Street

2154
Crossrail leadership team,
Crossrail’s Bond Street station.

The new Crossrail leadership team has developed a new plan to complete the outstanding works and bring the Elizabeth line into passenger service at the earliest possible date

Following a detailed audit of the programme, including what went wrong in the past, the new Crossrail leadership team has produced a plan to put infrastructure project back on track.

The new plan has required identifying and re-sequencing over 100,000 interdependent tasks and takes into consideration exactly what is left to be done and how long it will take.

As many risks and uncertainties remain in the development and testing of the train and signalling systems, Crossrail Ltd has identified a six-month delivery window with a midpoint at the end of 2020.

The central section of the Elizabeth line will open between Paddington and Abbey Wood and link the West End, the City of London, Canary Wharf and southeast London with initially 12 trains per hour during the peak.

It is expected that all stations on the route will open except for Bond Street which is delayed because of design and delivery challenges.

Once the central section opens, full services across the Elizabeth line from Reading and Heathrow in the west to Abbey Wood and Shenfield in the east, will commence as soon as possible.

As the completion work proceeds Crossrail Ltd will be providing Londoners with regular progress reports, and increasingly specific estimates of when the Elizabeth line will open. Crossrail Ltd has put in place a new visual management system to monitor progress by our contractors and their supply chains so that issues are addressed as quickly as possible.

There are four major tasks that still need to be completed include:

  • Build and test the software to integrate the train operating system with three different signalling systems
  • Install and test vital station systems
  • Complete installation of the equipment in the tunnels and test communications systems.

Crossrail expects that the remaining fit-out and systems installation in the stations and tunnels will be completed this year. The Crossrail leadership team also expects that Bombardier Transportation and Siemens will complete development of the train and signalling software this year.

The central section works are expected to be delivered within the funding package agreed by the Mayor, government and Transport for London in December 2018.

Mark Wild, chief executive of Crossrail Ltd, said: “I share the frustration of Londoners that the huge benefits of the Elizabeth line are not yet with us. But this plan allows Crossrail Ltd and its contractors to put the project back on track to deliver the Elizabeth line.

“Crossrail is an immensely complex project and there will be challenges ahead particularly with the testing of the train and signalling systems but the Elizabeth line is going to be incredible for London and really will be worth the wait. This new plan will get us there and allow this fantastic new railway to open around the end of next year.”

Tony Meggs, chairman of Crossrail Ltd, said: “Both the Crossrail Board and the Crossrail leadership team fully recognise the seriousness of the challenges we face. The Crossrail Board is pleased with the progress by the new Crossrail leadership team to get a grip on the project and pull together a robust and realistic plan to complete the Elizabeth line.

“An enhanced governance structure has been put in place to strengthen the Crossrail programme. The Crossrail Board will be holding the leadership team to account as they work to complete the railway. We will be open and transparent about our progress and will be providing Londoners and London businesses with regular updates as we seek to rebuild trust with all our stakeholders.”