NAO slams MoD for failing to ease risks on nuclear projects

293

The Ministry of Defence’s (MoD) poor management of three critical infrastructure projects on its nuclear-regulated sites has contributed to a cost increase of £1.35bn, according to the National Audit Office (NAO)

Not only has the poor management of these infrastructure projects led to cost hikes of £1.35bn, but it has also created delays of between 1.7 and 6.3 years, says the NAO.

Following issues in the early stages of the infrastructure projects, the MoD has made progress, with some of the construction now complete. However, it still needs to manage the remaining commercial risks and learn the lessons for future projects, according to the NAO.

The three critical projects are:

  • MENSA – A new nuclear warhead assembly and disassembly facility, valued at £1.8bn, at the Atomic Weapons Establishment (AWE)-operated site in Burghfield (Reading).
  • Core production capability (CPC) facilities – Upgraded facilities, costing at least £474m, at the Rolls Royce-operated site in Raynesway (Derby) to produce the latest nuclear reactor core designs.
  • Primary build facility – New facilities at the BAE Systems-operated dockyard in Barrow-in-Furness (Cumbria), costing £240m to upgrade ageing facilities and support improved submarine construction techniques.

Challenges faced by infrastructure projects

There are unique challenges with these projects. They include the need to comply with additional nuclear-related regulations, the limited pool of suppliers and the complexity of the designs. Problems in the earlier and riskier stages of these projects have caused delays and cost increases.

Some of the designs may have been more costly than necessary, mainly as a result of construction starting before the requirements or designs were fully developed, and changes to the project management or commercial approach. The way that the MoD set up the contracts also means that it, and not its contractors, must foot the bill for these cost increases as it did not share out the financial risks.

Broader consequences for nuclear work

The NAO states that the delays to these projects have broader implications for nuclear work, which the MoD must manage. For example, following delays to MENSA, the MoD and AWE had to continue using existing infrastructure. The MoD expects it will have spent £21m between 2016-17 and 2019-20 on site upgrades to continue to comply with regulations and be able to use the Burghfield site.

The MoD could have learnt more from the early stages of other nuclear infrastructure projects concluded in the UK and elsewhere.

All the infrastructure projects have now progressed and most of the facilities are taking shape. The MENSA facility was completed in October 2019, subject to fit out, and the first of the CPC facilities is expected to be completed in early 2020. Construction of one of the Primary build facility buildings is also largely complete.

The MoD has made changes to improve its oversight of infrastructure projects and its relationships with contractors and regulators.

Gareth Davies, head of the NAO, commented: “While these infrastructure projects are complex, the MoD has encountered similar challenges before in its nuclear work.

“Although it has recently introduced changes to enhance its oversight of the projects and improve its contracts with suppliers, it should have learnt earlier from past mistakes and the experience of others in the nuclear sector.

“Instead, the MoD’s failure to mitigate commercial and delivery risks early on has led to project delays and cost increases, as well as impacting its wider work.”

Editor's Picks

LEAVE A REPLY

Please enter your comment!
Please enter your name here