Increased construction costs for hospitals delayed by Carillion collapse

296
Carillion collapse, Increased construction costs,

The National Audit Office (NAO) has released its latest report, which shows serious delays and increased construction costs for two hospital developments due to the Carillion collapse

The 646-bed Royal Liverpool, which was due to open in June 2017, is now forecast to be completed more than five years late, in the autumn of 2022, and the Liverpool University Hospitals NHS Foundation Trust has not yet set an opening date.

The 669-bed Midland Metropolitan, which was originally due to open in October 2018, is now expected to open in July 2022.

The government ensures that most of the increased construction costs so far have been borne by the private PFI investors and Carillion, rather than the taxpayer, according to the new investigation by the NAO.

Increasing construction costs

It is now predicted to cost a total of £1,063m to build and run compared to the original £746m. The taxpayer is currently expected to pay £739m of this, a reduction of 1% from what was originally planned.

The Midland Metropolitan is due to cost at least £988m in total to build and run – over £300m more than the original £686m.

The taxpayer is currently expected to pay £709m of this, an increase of 3% from what was originally planned.

There were significant construction problems and delays before Carillion went into liquidation on 15 January 2018 but the contractor’s collapse created more delay.

Public financing to complete the hospitals

Work on both sites stopped while the hospital Trusts, government and the private investors attempted to rescue the projects. By September 2018, these attempts had failed; government decided to terminate the PFI schemes and provide public financing to complete the hospitals.

The full extent of construction problems at Royal Liverpool began to emerge after Carillion collapsed and over the course of 2018. The new construction contractor has had to strip out three floors of the building and start major work to reinforce the structure with steelwork and additional reinforced concrete.

The Department of Health & Social Care (DHSC) paid £42m compensation to Royal Liverpool’s investors to terminate the PFI contract. The contract required the Trust to pay compensation to the PFI company’s lenders, based largely on the estimated cost to complete the hospital, before the actual cost to complete the hospital was known.

Had the Department and Trust better understood the cost to complete the hospital, they may not have paid anything to the lenders. The estimated cost of completing the hospital has risen from £117m in September 2018, when DHSC agreed the termination payment, to £293m now.

New suppliers for both the Trusts

After the termination of the PFI contract, in order to restart the Liverpool project without further delay, the Liverpool Trust agreed contracts with several new suppliers without a public procurement process. The Sandwell and West Birmingham Hospitals NHS Trust ran a public procurement for the contract to complete Midland Metropolitan taking 15 months, which only attracted one viable bidder.

Both Trusts are now directly managing the contracts with new construction firms. At Midland Metropolitan, the Sandwell Trust has negotiated a ‘target price’ for work by its new contractor, Balfour Beatty, and prices should not rise unless the Trust changes the scope of the project or there are unforeseen problems with Carillion’s work.

At Royal Liverpool, the new main contractor, Laing O’Rourke, has no contractual incentives to control costs. NHS England and NHS Improvement has worked with the Liverpool Trust to develop additional oversight arrangements such as using an independent construction consultancy to advise on the appropriateness of costs.