Cleveland Bridge to deliver modular bridge on A19 Testo’s scheme

255
A19 Testo, bridge,

Cleveland Bridge UK has secured the A19 Testo’s Junction Improvement Scheme to fabricate and install a new 141.4m bridge at the centre of a flyover

As part of Highways England’s A19 Testo’s Junction Improvement Scheme, Cleveland Bridge UK has been awarded the project by Costain to fabricate and install a new 141.4m bridge at the centre of a flyover.

Further alleviating traffic congestion on the redeveloped roundabout that connects the A19 with the A184, the flyover is part of a five-year £15bn programme by Highways England to improve journeys between the main North East arterial route and the surrounding areas.

To date, two additional lanes on both northbound and southbound sides of the roundabout have been finished, which has also created the space for the construction of the flyover that includes the installation of more than 130 concrete piles.

Fabricated bridge

The 1,393te weathering grade road bridge will be fabricated as a series of 25 paired girders at Cleveland Bridge UK’s 27,000 square metre production facility, 40 miles south of the project site.

The scale of Cleveland Bridge UK’s factory will also enable it to undertake a test assembly of the structure, which will ensure a more efficient final installation on site later this year.

Chris Droogan, managing director of Cleveland Bridge UK, said: “We are highly active in markets across the world, but it is always satisfying to secure projects in our home region of the North East, particularly those that will bring significant benefits to the efficiency of the area’s transport network.

“We are also very proud to continue our long-term collaborative relationships with Highways England and Costain and look forward to the successful delivery of this project.”