Infrastructure maintenance work to commence in Leeds

950
Regent Street Flyover

Construction work has progressed at pace to demolish and rebuild the southern bridge section of Regent Street Flyover and the project is now entering the next phase where the northern bridge will be taken down and rebuilt

Construction started in summer last year on the bridge which carries traffic over the A61 Regent Street.

A contraflow has been in place for the duration of the work with traffic flowing in both directions on the eastbound carriageway of the A64(M).

With the transition to the next phase, the two-way flow of traffic will be moved to the westbound carriageway and on to the newly constructed southern bridge, with the eastbound carriageway closing to all traffic from North Street to Burmantofts Street.

The contraflow switch is expected to happen during night closures of the A64 and A64(M) Inner Ring Road between Tuesday 4 May and Thursday 6 May between 8pm and 5.30am.

Following this, the A61 Regent Street, A64 and A64(M) Inner Ring Road will be closed from Friday 8pm to Monday 5.30am for four consecutive weekends for the demolition of the northern bridge.

The A64(M) westbound off-slips to the A61 Eastgate/Leeds Playhouse and North Street are expected to reopen by the end of May.

The work is set to be fully complete by spring 2022.

Progression to the next phase of a major project

Leeds City Council‘s chief officer for highways and transportation, Gary Bartlett said: “This past year has been challenging but I’m pleased to see that the programme is on schedule and we are now progressing to the next phase of this major project.

“We are in close conversation with businesses in the area to mitigate the impact of these road closures and our contractors have worked to rejig the programme slightly so the diversions are in place for as little time as possible.”

Editor's Picks

LEAVE A REPLY

Please enter your comment!
Please enter your name here