Terminating a construction contract – the end of your troubles or the start?

6926
Terminating a construction contract
© Joanne Zhe

Sarah Evans, construction partner at law firm Spencer West, explores the factors to consider when terminating a construction contract

Whilst construction projects should always aim to create a harmonious supply chain marriage, often parties find themselves heading for divorce. And never more so than in this post-covid, post-Brexit era, where issues around lack of materials and resources, quality of work, delays to completion, cashflow and payment frequently prove incapable of resolution by collaboration.

Supply chain members are left frustrated, feeling they have no alternative but to terminate relationships early. But, just like a divorce, termination is serious, often with no clear-cut innocent party. It requires adherence to strict procedures and holds dire financial consequences for those getting it wrong.

When can a construction contract be terminated?

There are limited ways to terminate including:

  1. By agreement

The parties can agree to terminate on commercial terms. Recording these terms in a formal settlement agreement will minimise the scope for further dispute. This is the amicable divorce, where relationships can be preserved with an early conclusion and there are no arguments over procedural irregularities (see further below).

  1. Pursuant to the terms of the contract

  • Termination at will. Some contracts allow a party to terminate the contract without having to give any reasons. These ‘termination at will’ clauses can take effect quickly and limit what sums the terminated party can recover on termination, including loss of profits for the entire works. They are useful clauses for employers. However, contractors and subcontractors faced with these clauses at the outset of the contract should try to get them removed. If not, they should negotiate the longest notice period possible. This will enable them, if terminated, to move onto other projects and minimise their financial losses.
  • Termination for breach. Not every breach allows you to terminate. This will be dictated by the terms of each contract.

There may be a contractual right to terminate where there has been a material breach of one or more terms and provisions of the contract. Frequently this right is dependent on the terminating party serving a notice detailing the breach, giving the recipient a specified period to remedy it and their failing to do so. Where there is no definition of ‘material breach’ within the contract, the Courts have ruled that it will depend on the factual circumstances of each case.

What about non-payment? Termination may be possible. For example, under the JCT SBC and DB 2016 forms a contractor is entitled to terminate its own employment where an employer fails to pay an amount due by the final date for payment. There must be service of a first (default) notice and the employer must continue the default for a specified period before the contractor can serve the termination notice.

One of the most fiercely contested grounds for termination is where it is based on a ‘failure to proceed regularly and diligently’. The employer’s right to terminate a contractor’s employment on this ground is contained within both the JCT SBC and DB 2016. Again, this right is subject to strict provisions on service of notices and the contractor failing to remedy the default. What constitutes a failure to proceed regularly and diligently is a hot topic; often, as with the standard JCT contracts, there is no express definition.

Whilst attempts at a clear and unambiguous definition have been made, the Courts have found it an impossible task, saying that it’s like the elephant – you know it when you see it.

Again, it will come down to the facts of each case. Generally, delay alone will not be proof of a failure to proceed regularly and diligently but may call for further investigation. Evidence of a failure to achieve programmed productivity and a failure to properly resource may help. The key to proof will be good contemporaneous records, for example consistent complaints in writing and regular records of the amount of personnel on site. Independent expert evidence may ultimately be required.

  • Termination for insolvency.

Some contracts, including some of the standard industry forms, contain express rights for employers, contractors and subcontractors to terminate in the event of the insolvency of another party. What constitutes insolvency will be contract specific.

However, these contractual rights cannot now be viewed in isolation. The Corporate Insolvency and Governance Act 2020 (CIGA), which came into effect on 26 June 2020 made an amendment to the Insolvency Act 1986. This now precludes a supplier of goods and services from exercising a right of termination against a company going through an “insolvency” procedure (defined in CIGA). Employers are largely unaffected. But in many cases contractors and subcontractors will no longer be able to rely on their contractual rights to terminate for upstream insolvency and to collapse the supply chain.

  1. At common law

English common law also provides for the repudiation of a contract where there has been a fundamental breach, being one going to the root of the contract. Great care will be needed if termination on this basis is being considered.

You have the grounds, but how do you terminate?

To terminate lawfully, it is also vital to follow the prescribed procedures for termination notices to the letter.

  • Method of service. Whilst contracts generally provide for the methods of service of notices and other communications, stricter methods can apply to termination notices. It cannot be assumed, even in these times, that service by email will suffice. Standard contracts such as the JCT SBC and DB 2016 contain specific requirements for termination notices to be delivered by hand or sent by Recorded Signed for or Special Delivery Post.

The notice must also be served on the address and persons prescribed by the contract.

  • Who serves the notice? Contracts vary greatly as to who is responsible for serving notices of termination. For example, in the case of JCT SBC 2016 the architect or contract administrator must serve the first (default) notice with the employer serving the second (termination) notice. Conversely, with JCT DB 2016, it is the employer or employer’s agent (under Article 3) who must serve both notices.

The risks of termination and how to mitigate them

If the terminating party fails to satisfy the grounds for termination and/or to follow the prescribed procedures, the recipient can hold them in repudiatory breach of contract and claim substantial damages. The tables are then suddenly reversed.

The success of termination arguments on both sides will largely be dependent on good records and evidence. Given the risks of getting things wrong, it is vital that a terminating party ensures those records and evidence are in place prior to termination.

For a terminating employer, getting the works completed after termination will be paramount. Planning before termination who will carry out the works, how and for what payment, will be key to a smooth transition. Without this, the termination of a contractor may trigger the immediate termination of all subcontractors and suppliers and bring a project to an abrupt and protracted halt.

For contractors and subcontractors, being on the receiving end of a termination notice is likely to spell severe cash flow challenges. Under some JCT provisions, there will be no immediate final account. They may be entitled to payments that have already become due, but the final reckoning will only usually take place after the employer has arranged for completion of the works, the making good of defects has occurred and a termination account has been prepared. That may be months or years away.

Any disputes arising over termination will be subject to the dispute resolution provisions in the contract. Worst case, this may mean lengthy litigation or arbitration. Adjudication, if applicable, can short circuit this. For contractors and subcontractors, this swift and low-cost process could reverse the cash flow challenges of being terminated and facilitate recovery of substantial damages for repudiatory breach.

Termination – last resort

Termination should always be viewed as a last resort, deployed only when other viable routes of preserving relationships have been exhausted.

If you find yourself involved in a termination situation from whichever side, do study your contract and take early legal advice. There is so much to get right to ensure termination gets you to where you really want to be.

 

Sarah EvansTerminating a construction contract

Partner construction, engineering, infrastructure and energy projects

Spencer West LLP

sarah.evans@spencer-west.com

07958 627977

www.spencer-west.com

Editor's Picks

1 COMMENT

  1. What if I don’t have a contract with a builder that is refusing to give a breakdown of cost’s for the job can I just walk away , we feel he is being under handed and dishonest.

LEAVE A REPLY

Please enter your comment!
Please enter your name here