The next phase of façade remediation: Why building owners need to move from compliance to action

25
The next phase of façade remediation: Why building owners need to move from compliance to action
Image: iStock | © Bjoern Wylezich

Russell Wright-Turner, director, Walker Sime, explores the practical challenges facing building owners, from understanding the condition of their existing façades and identifying risks to planning, budgeting and delivering remediation programmes

Despite significant progress in identifying unsafe building façades, the pace of remediation remains a challenge across England. Government figures for September 2026 indicate that approximately 45% of residential buildings over 11 metres being monitored for unsafe cladding had yet to commence remediation.

The Building Safety Act 2022 has already brought significant changes to building safety responsibilities, while the proposed Building Safety (Remediation of Unsafe Cladding etc) Bill, introduced in October 2026, represents a further move towards greater accountability and faster remediation.

The proposals include new duties to assess and remediate unsafe external walls, stronger enforcement powers, and a mandatory register of medium-rise residential buildings. For building owners, this places greater emphasis on understanding the condition of their properties and establishing a clear route towards making them safe.

However, identifying a safety concern and delivering the necessary remediation are two very different challenges. Complex ownership arrangements, incomplete building information, funding uncertainty and lengthy approval processes can all prevent projects from progressing. Addressing these issues requires building owners to consider not only their regulatory responsibilities, but also the technical, commercial and practical implications of remediation from the earliest possible stage.

Advertisement

Understanding the condition of existing buildings

One of the biggest challenges in façade remediation is establishing how a building was originally constructed and understanding the full extent of any defects. Many existing buildings were constructed over several decades under different versions of the Building Regulations, and records of how their façades were actually built are not always complete.

This means building owners cannot always rely on existing documentation or visual inspections to establish whether a façade is safe. More detailed investigations, which can involve opening up sections of the external walls, may reveal concealed defects such as missing cavity barriers, inadequate fire stopping or combustible materials.

What initially appears to be an isolated defect can quickly become a much wider remediation exercise, with significant implications for cost, programme and disruption.

The situation becomes more complicated when original developers, contractors or specialist suppliers have become insolvent or ceased trading. This can leave building owners with limited access to historic design information and uncertainty around potential routes to recover costs through warranties, contractual claims or insurance.

Ownership arrangements present further difficulties – a building may involve institutional investors, freeholders, resident management companies and multiple leaseholders, each with different financial interests and responsibilities.

Establishing who has the authority to commission investigations, approve expenditure and progress remediation can be as challenging as determining the appropriate technical solution.

For building owners, the priority must therefore be to understand the building, its ownership structure and the potential financial exposure before committing to a remediation programme. Without this clarity, even projects with an identified technical solution can struggle to move forward.

From technical assessments to a deliverable strategy

The starting point for any remediation programme should be a thorough assessment of the existing building rather than an assumption about the work required. This involves reviewing available design information, undertaking suitable fire risk appraisals of external walls in accordance with PAS 9980:2022 where appropriate, and carrying out proportionate intrusive investigations by competent specialists.

However, technical investigations should not take place independently of cost and programme planning. Early commercial input can help building owners understand the financial implications of different remediation options, establish appropriate contingency allowances and assess whether proposed solutions are realistic and affordable.

At Walker Sime, we bring the relevant specialists together from the outset, challenge assumptions, and develop a coordinated strategy that considers technical feasibility, statutory approvals, procurement, access arrangements, cost, and programme. This provides building owners with greater clarity before committing to significant expenditure and reduces the risk of unexpected costs or delays emerging later in the process.

Communication is equally important, particularly where remediation is being undertaken in occupied buildings. Managing agents, residents and other stakeholders need to understand what is proposed, how works will be delivered and what disruption they may face. Engaging these groups early can help manage expectations around access, timescales, safety arrangements and the impact on day-to-day occupation.

The objective is to develop a remediation programme that is technically appropriate, commercially viable, and deliverable.

Why remediation projects continue to stall

The government’s Remediation Acceleration Plan is supported by an estimated £9.2 billion funding framework, incorporating central government investment, anticipated Building Safety Levy receipts and the recovery of costs from developers responsible for historic defects.

However, this does not represent a fully funded solution to all outstanding remediation work – establishing eligibility for available funding and identifying the parties responsible for meeting costs and resolving potential claims can create considerable uncertainty for building owners. Regulatory approvals add another layer of complexity, as for higher-risk residential buildings, typically those over 18 metres, the Building Safety Regulator’s approval process can have significant implications for project programmes.

In our experience, approval periods can extend to 25 to 45 weeks, creating uncertainty around procurement, construction commencement, and overall project costs.

Incomplete investigations, design coordination challenges and the availability of specialist contractors can also affect progress, particularly where works must be undertaken while residents remain in occupation.

These constraints demonstrate why realistic programming and proactive cost and project management are essential. Building owners need to account for the potential impact of regulatory processes and specialist availability when establishing delivery timescales, rather than treating these as issues to resolve once the project is underway.

Taking a more proactive approach

For building owners who know remediation is required but remain uncertain how to proceed, allowing questions around funding, design or responsibility to delay progress can create further difficulties.

The priority should be to establish a structured, risk-based strategy, beginning with the appropriate assessment and management of immediate safety concerns. Targeted investigations can then establish the full extent of the work required, while early commercial and project management input helps determine how remediation can be delivered within realistic financial and programme constraints.

A comprehensive cost plan should consider not only construction works, but also professional fees, access arrangements, resident protection, statutory approvals and appropriate contingency allowances. Building owners should also establish funding eligibility and responsibility for remediation costs as early as possible, alongside engaging residents and other stakeholders in the proposed approach.

There are also important commercial reasons to act; unresolved façade safety concerns can affect property valuations, mortgage availability, and leaseholders’ ability to sell their homes. Prolonged uncertainty can therefore have implications that extend well beyond regulatory compliance.

Ultimately, the lowest initial remediation cost does not necessarily represent the best long-term value. Poorly coordinated design, procurement and delivery can result in variations, additional expenditure and prolonged disruption.

As regulatory expectations continue to evolve, building owners need to turn assessments and technical findings into clear, commercially viable remediation programmes. A coordinated approach that considers safety, cost, responsibility and delivery from the outset will be essential to overcoming the barriers that continue to hold projects back, protecting asset values and, most importantly, delivering safer buildings.